26 Heatsink Installation
Chapter 4
19. Carefully turn the cam lever to lock into place. (See Figure 18.)
Figure 18. Turning the Cam Lever
20. Ensure the cam lever is locked into the retention frame. (See Figure 19.)
Figure 19. Cam Lever Locked into Retention Frame